Our own foaming plant in Huangjiang, Dongguan

Pouring, foaming, trimming, sewing, packing and shipping all happen in one plant. Three foaming lines, about 150,000 pieces a month.

A half-carousel foaming line with the green foaming machine at its center
Half-carousel foaming line, about 35,000 pieces a month

From a drum of raw material to a carton of pillows

Here is the line in production order. Every step happens in this one plant.

  1. A worker beside the running carousel foaming line

    Pouring and foaming

    The two components are poured into the molds at the day’s formula ratio and cure as the carousel turns. We run 3 dual-formula foaming machines with 200 kg tanks, putting 85 to 90 sets of molds and 6 formulas on the line each day.

  2. Workers trimming foam cores at a long table, with trimmed cores on shelves beside them

    Trimming, one by one

    Every core out of the mold is trimmed by hand and inspected as it is trimmed. This is a 100% inspection; rejects are pulled on the spot.

  3. Rows of racks holding yellow and white foam cores

    Cores on the racks

    Inspected cores wait on racks for their covers. 300 racks at 200 × 80 cm hold 30,000 pillows or 50,000 lumbar supports and seat cushions.

  4. Rows of workers sewing pillow covers in the sewing workshop

    Cutting and sewing covers

    Fabric is cut to pattern and four-thread overlocked. Finished covers are inspected on their own before they meet a core.

  5. The packing line conveyor and an automatic roll-packing machine

    Covering and packing

    Pillows are covered on the packing line, then roll-packed or boxed flat. 2 automatic roll-packing machines and 12 packers handle 3,500 sets a day, checking every cover again for marks, loose threads and creases.

  6. Neatly stacked, shrink-wrapped cartons of finished goods in the warehouse

    Warehouse and AQL before shipping

    Finished goods are stacked by order in a 1,500 m² warehouse that holds 50,000 to 80,000 pieces. Every shipment is AQL-sampled before it leaves.

Floor space, lines and machines

These figures come from the plant’s equipment and capacity list.

Equipment

MachineCountUse and specs
Dual-formula PU foaming machine3200 kg tank each
10 m automatic carousel foaming line1~80,000 pieces a month
Half-carousel foaming line2~35,000 pieces a month each
Automatic foam press1
Jack four-thread overlock machine20Cover overlocking and sewing
Automatic roll-packing machine2Roll-packed shipping
Racks300200 × 80 cm; hold 30,000 pillows or 50,000 lumbar supports and seat cushions
Temperature and humidity test chamber1Roll-pack rebound and aging tests

Nine checks, two of them on every piece

From the client’s approved pre-production sample to the AQL check before shipping.

  1. Approved pre-production sample

    The client approves a pre-production sample; the first article and the bulk order are both checked against it.

  2. Pre-production meeting

    Process requirements and watch-outs are agreed before work starts.

  3. Formula set-up and first article

    The formula is tuned for the order and the first article is checked against the approved sample and logged.

  4. First sort of cores

    Cores are sorted right after demolding; anything doubtful goes no further.

  5. Foaming line patrol

    QC patrols the foaming line; every batch is weighed by one person and checked and signed by another.

  6. Trimming, every core

    Each core is inspected as it is trimmed.

    100% inspection

  7. Packing, every cover

    Each cover is checked for marks, loose threads and creases as it goes on.

    100% inspection

  8. Packing line patrol

    QC patrols the packing line.

  9. AQL before shipping

    Every shipment is AQL-sampled. You are welcome to inspect on the line.

Four things we manage by

  • Standard processes
  • Recorded data at every step
  • Clear ownership of every area on the floor
  • Quality raw-material suppliers

Certification and testing

ISO 9001
Certified quality management system.
Product testing
Products can be tested to Chinese national standards and for RoHS, pH, formaldehyde and roll-pack rebound.
Export
We ship to Europe and North America, Japan and Korea, Southeast Asia and across China.

Before mass production: a week at 55 °C, half a day at 0 °C

The factory’s temperature and humidity test chamber
55 °C × 7 days
Every design that ships roll-packed is rolled and kept in the humidity chamber at 55 °C for seven days. Production starts only if it springs back within seconds.
0 °C × half a day
So the foam won’t stiffen in winter, cores spend half a day at 0 °C before mass production. No noticeable hardening, or no production.

Written down every day

The foaming machines are calibrated daily. Every batch is weighed by one person and checked and signed by another. First articles are checked against the pre-production sample the client approved.

Flow calibration log for the foaming machine
Formula and batching record sheet
First-article inspection record

Machine flow calibration log

Studio photo of a model holding up the Twin-Heart Butterfly Pillow

Get one in your hands first

Tell us which pillows you’d like to see, rough quantities and where you sell, and we’ll send samples. Or bring your own idea — we can tool a design that’s yours alone.

Request samplesHow OEM / ODM works